Carlton SWCD improves road safety, reconnects Lake Superior to trout stream in Nemadji River watershed

--

Rebuilt, free-flowing stretch of Skunk Creek is among Clean Water Fund-backed projects that remove experimental, 1970s structures — with help from Minnesota DNR, U.S. Fish & Wildlife Service, Carlton County Transportation Department

A Carlton SWCD project moved Skunk Creek away from a county road and, farther downstream, removed a structure built in the 1970s to stabilize the road by diverting the creek into a concrete culvert. The project, which finished in August, reconnected a stretch of trout stream to Lake Superior. A Clean Water Fund grant from the Minnesota Board of Water and Soil Resources is in play. Photo Courtesy Carlton SWCD

CARLTON — A county road in danger of slumping into Skunk Creek was stabilized and the first stretch of a trout migration route from Lake Superior was restored this summer in Blackhoof Township south of Carlton.

The $518,830 Carlton Soil & Water Conservation District project moved Skunk Creek away from Carlton County Road 103, residents’ and emergency responders’ only access to the area when the Nemadji River floods Minnesota Highway 23. One month after construction finished, on Sept. 30 the project withstood a 200-year flood that brought 5 to 6 inches of rain within six hours and caused the Nemadji River headwaters to rise more than 10 feet.

It’s not an ideal situation to have a 200-year flood event immediately after you complete construction that involves in-stream structures or channel modifications,” said Will Bomier, Carlton County Transportation Department permits and right-of-way technician. “The project functioned as planned, and it was amazing to see the process of sediment transport and floodplain connectivity return to this area after 50-plus years.”

The 1970s structure, seen in 2017, was an experimental design meant to reduce sediment and stabilize the road by routing Skunk Creek through a concrete culvert. Engineers had predicted water might top the concrete weir once every four years. Recently, that had been happening at least once a year. Photo Credit: Ann Wessel, BWSR

At a second site downstream, contractors removed a 1970s structure — an experimental design meant to reduce sediment and stabilize the road by diverting the creek into a concrete culvert. Over time, erosion had blocked fish passage and chewed away at the road’s edge. In recent years, water topped the concrete weir at least once a year — something engineers had estimated might happen once every four years. The 1970s project forced a 20-foot stream through a 4-foot pipe.

“When you do that, you get the firehose effect. You get a huge increase in velocity,” Bomier said. “The fish aren’t able to move up that pipe because the water is too fast for too far.”

The project reopened nearly 7 miles of cold-water trout stream — including nearly 3 miles of Skunk Creek’s main stem, the entire 3.5-mile stretch of Duessler Creek and just over a half-mile of Elim Creek.

“It’s the key, the first one in the series that blocks fish passage,” said Melanie Bomier, Carlton SWCD water resources technician.

The 1970s structure forced the 20-foot-wide stream, seen here in 2017, through a 4-foot pipe. Over time, erosion had blocked fish passage and eroded the edge of a county road. Photo Credit: Ann Wessel, BWSR

The project will keep an estimated 226 tons of sediment — more than 17 dump truck loads — out of the Nemadji River annually. The Nemadji River flows into Lake Superior. Had the undersized pipe clogged, it could have caused a structure failure with the potential to release the equivalent of 600 dump truck loads of sediment.

Funding included a $414,830 Clean Water Fund grant from the Minnesota Board of Water and Soil Resources. Partners included the Carlton County Transportation Department, the Minnesota Department of Natural Resources and the U.S. Fish & Wildlife Service.

The SWCD and transportation department collaboration began with a spring 2017 culvert inventory and several culvert designs made possible through a $103,220 Enbridge Ecofootprint grant.

Flooding twice delayed work on the Skunk Creek project, most recently in June 2018. But Melanie Bomier said the SWCD saved money by seeking bids in December when contractors were less busy. The project came in under budget. The final amount hinges on the cost of next spring’s tree and live-stake willow and dogwood planting.

The 1970s culvert and pipe project, seen here in 2017 from Carlton County Road 103, was meant to showcase drain tile and slope techniques that were new at the time. The site was chosen because it was easily visible from the road. Photo Credit: Ann Wessel, BWSR

Originally, the 1970s culvert and pipe project was a collaboration among the SWCD, transportation department and township meant to showcase new drain tile and slope techniques. The site was chosen because it was easily visible from the road.

Once again, the site will serve as a demonstration — this time to show how red clay dam removal can work elsewhere in the Nemadji River watershed. To date, Carlton SWCD has removed four of the 16 structures prioritized in an inventory funded by an Environmental Protection Agency grant. Those that remain include a 40-foot dam.

“Now they have a place where they can see what it looks like,” Melanie Bomier said. “When you have a pond, it’s hard to imagine it as a stream. Most of these dams are way back in the woods and hard to access. This, people drive past every day.”

David Cartwright, a business manager for a local trade union in Duluth, is among the daily commuters.

Carlton County Transportation Department video

Cartwright lives on 20 acres between Skunk Creek and the Nemadji River, which he bought as hunting property. He allowed contractors to spread nearly 600 dump truck loads of clay removed from the Skunk Creek project site on his land, which will level it out and make deer habitat easier to maintain.

He’s among the half-dozen residents who were in danger of becoming stranded if County Road 103 and Highway 23 both flooded.

Daily traffic counts on County Road 103 average 50 vehicles. Will Bomier said that number doubles when other roads close.

Melanie Bomier described the need for the upstream work on Skunk Creek, where two banks were slumping: “After every rain event, the road slope was sloping into the stream. There was the danger that we were going to lose the road.”

The Skunk Creek site is part of Carlton SWCD’s continuing red clay dam removal project. After two years of flood-related delays, work started this season and finished in August. Willow and dogwood live stakes will be planted next spring, when they have the best chance of taking hold. Photo Courtesy Carlton SWCD

This summer, contractors moved two 70-foot-long segments of the curving stream farther away from the highway. To attain optimal flow, the rerouted stream incorporated width and length calculations plus floodplain connections.

Toe-wood structures armored the banks and diverted the fast, erosive flow. Strategically placed root balls (trees with roots attached) plus boulders diffused and directed the water. Rock J-hooks (lines of rocks angled upstream and then curved in mid-channel) helped to keep water from scouring the banks and created velocity-slowing pools. The reconstructed stream segments are a series of pools and riffles.

At the shorter and straighter culvert-and-pipe removal site downstream, the design incorporated more J-hooks.

While he’s not an avid trout angler, Cartwright said he could appreciate the reconnected fish passage plus improved road safety.

“I’m hoping it takes away the chance of that happening, the roads washing out. Having the trout stream would be good for everybody,” Cartwright said.

Project funds

Major funding sources include the following. Project tallies are still being calculated; final touch-up work is slated for next spring.

· $414,830 Clean Water Fund

· $51,170 U.S. Fish & Wildlife Service Fish Passage Program

· $50,000 Carlton County Transportation Department, in-kind estimate to date

The Minnesota Board of Water and Soil Resources’ mission is to improve and protect Minnesota’s water and soil resources by working in partnership with local organizations and private landowners. Website: www.bwsr.state.mn.us.
The 4-foot opening, seen here in 2017, resulted in a “firehose effect.” The increased velocity was another factor blocking trout from migrating upstream. Photo Credit: Ann Wessel, BWSR

Stocking would boost reconnected trout streams

The Minnesota Department of Natural Resources could stock Skunk Creek as early as 2024 with a wild strain of broodstock it is currently developing.

The DNR had planned to stock 6,750 fingerlings in Skunk Creek, 2,625 in Duessler Creek and 2,250 in Elim Creek each year for three consecutive years starting in May 2019. Subsequent electrofishing assessments would determine if any natural reproduction took place. But that source, the U.S. Fish & Wildlife Service’s Lake Superior strain of native brook trout from Tobin Harbor on Isle Royale, Michigan, was affected by disease.

Fishing license fees and trout stamps help to pay for fish stocking.

Skunk Creek’s main stem is nearly 9 miles long. The project would reconnect 7 miles of designated trout stream — including nearly 3 miles of Skunk Creek, nearly 3.5 miles (the entire length) of Duessler Creek, and more than a half-mile of Elim Creek.

Skunk Creek and its tributaries contain 15.8 miles of stream within the 276-square-mile watershed.

“It may take some time for fish to start finding this area again,” said Deserae Hendrickson, the DNR’s Duluth-based area fisheries supervisor. She explained that fish will stop migrating if they can’t get past a barrier to spawn. “The resident fish that we’re stocking will be spreading out and inhabiting the stream, hopefully.”

Trout live one to three years in a stream until they undergo smoltification, the adaptation from freshwater to seawater that triggers their migration to the lake and then back to spawn.

“I’m pretty excited about reintroducing some connectivity within the watershed, especially if we’re able to get funding to continue removal of the other structures within the Skunk Creek watershed,” Hendrickson said. “That could really be a huge benefit to restoring the ecosystem.”

“The more of those that we’re able to restore to free-flowing and connected channel, the healthier that watershed is going to be, and the more likely that the fish we’re going to reintroduce will … survive and thrive within the stream,” Hendrickson said.

A sufficient base flow and natural springs keep Skunk Creek cold enough to support trout.

If efforts are successful, anglers could expect to start seeing decent-size fish about three years after they are stocked.

--

--

Minnesota Board of Water and Soil Resources
Minnesota Board of Water and Soil Resources

Written by Minnesota Board of Water and Soil Resources